Excel VBA Course
Excel VBA Course - From Beginner to Expert

200+ Video Lessons
50+ Hours of Video
200+ Excel Guides

Become a master of VBA and Macros in Excel and learn how to automate all of your tasks in Excel with this online course. (No VBA experience required.)

View Course

(80% Discount Ends Soon!)

Close Window (X)   
Excel VBA Course
[80% Discount] Excel VBA Course - From Beginner to Expert

200+ Video Lessons
50+ Hours of Video
200+ Excel Guides

Become a master of VBA and Macros in Excel and learn how to automate all of your tasks in Excel with this online course. (No VBA experience required.)

View Course

(80% Discount Ends Today!)

Define A 4 Day Work Week

Is there a way to redefine a work week to be 4-day (Mon-Thurs.).

I need to calculate start and end dates based on a net amount of work days.


For instance, if the start date is 8/9/2010 and the 'job' will take 14 working days (based on a 4-day week) what will be the end date?

Thanks,
Eitan


Excel VBA Course
Excel VBA Course - From Beginner to Expert

200+ Video Lessons 50+ Hours of Instruction 200+ Excel Guides

Become a master of VBA and Macros in Excel and learn how to automate all of your tasks in Excel with this online course. (No VBA experience required.)

(80% Discount Ends Soon!)

View Course




Similar Topics







I'm trying to come up with a solution to calculate the man hours and days worked over multiple sheets.

I have a file that has 8 sheets. the first seven sheets are the days of the week and the 8th sheet is where I want to calculate the hours.

The days of the week consists of "Name" "Date" Hours"

The 8th sheet consists of "Name", "Days of the week in their own column (7 columns in total)", "Total Hours" and "Total Days Worked"

Now... each day is always a different group and what I'm hoping for is to create a formula that can grab each name with their hours and throw them into the 8th sheet. So when the end of the week is done I have all the Employees weekly hours and days worked all finished.

I hope this makes sense. This file is to track about 100 employees that are on a rotational work schedule.

I have attached a sample file.

Thanks in advance for your help.


I need a formula to calculate overtime, after a work week of 40 hours.

for example: if an employee works 10 hours a day we would not count towards overtime until the employee completes a 40 hour work week.

Any suggestions would be greatly appreciated!!!!!

Thanks,
YV


I was able to convert start date and and end date to the number of days
inbetween the two dates. Does anyone know how to then convert the number of
days into months?



Hello,

I have two columns of data: column A contains the date and time in the form dd/mm/yyyy. Column B contains a number value. All the times are in order, so column A looks like:

01/01/2007
02/01/2007
03/01/2007

I have data from 2007 to 2010. I need to calculate an average daily value (in column B) for each month, and display it in column C. So, for January, I need to calculate the average of 31 days, February, 28 days, etc.

Is there a function I can use to do this? I've been trying the AVERAGEIF formula but can't get it to work. Any ideas would be much appreciated!

Many thanks,
Caitlin


A previous poster explained what I also need; there were no responses,
so I thought I would try again.

Does anyone know of an Excel template--or a small stand-alone
program--that will calculate the interest/principal breakdown when
payments are varied in amount and frequency? Free or low-cost, please.
I need one that will work on my Mac/Office 2004. I will need to print
out periodic reports.

Here is the way the previous poster described it:
"Excel template: Loan Amortization for random/irregular payments,
figures days
between payment dates.
I have a loan with a variable beginning balance and irregular payments
with
annual large payment. (based on collections)
Would like to enter payment and date.
then Excel would figure days since last payment, interest amount,
principal
amount, Ending Principal balance.
And total interest paid, total pricipal paid
If I change the starting principal, excel would recalculate all
entries."

Thanks very much.




Is there a way to calculate the average days between a column of dates?

Basically, I've got a sheet that contains a table of entries, and each entry gets a date stamp in the first column. I would like to have the sheet display the average time, in days, between entries. Is this possible?

Thank you in advance!
~cp


Peace to you all
I'm still new here but after I searched the forum I found great work done
for the needy like me.
So I'm so hopeful
I'm concerned with making a timetable for my school which we used to do it manually
I need a code to distribute each teacher timetable with the following basis:
the number of classes_ the teacher is assinged to work with_multiplied by the number of periods ( which is changeable ).
e.g ; Teacher 1 has 2 classes (1-1 &1-2). Each class should be visited 9 timea a week.
So Teacher 1 should work 18 periods a week
the distribution I need 'd look like the example in Sheet("timetable")
Please don't let me down
any help 'd be greately appreciated


I am trying to correct a formula for a productivity worksheet in excel. The idea is that we would have the ability to input the number of hours worked each day and the number of direct hours (working with clients) per day. Then take the daily percentages and add them then devide them to determine the final productivity percentage for the week. Additionally not everyone works a full week so I would need it to only divide the percentages of the days that were completed. Any suggestions? or does anybody know a formula that would accomplish this already? I am good with basic excel and was able to identify a flaw in the current productivity sheet.


HI...can anyone help me with a formula for aging data in days (to be aged based on current date vs. for eg., Invoice date)


Hello, please help me out with this one.

So I am at work workin on this report and I need a function that will make Excel automatically insert the today's date in a cell (let's say D90) when I fill the content of another cell (for example C90) and the that will be inserted will never change. I tried to use the =TODAY( ) function but it keeps updating the date in the cell to the current date if i reopen the worksheet 2 days later. I need the cell to keep in the cell the date of the day when I filled in the content of cell C90 and do not updated it every time i open the document to the actual date.. Thanks in advance!!


I have a spreadsheet counting down the days until a date is reached. However, after that date is reached and passed I get a #NUM! error.

What can I do to countdown the days as below AND countdown the days that have passed as a NEGATIVE NUMBER???


=DATEDIF(NOW(),D11,"D")


Good afternoon!

I'm working with Excel 2003 sp 3 on Windows xp.

I have been banging my head trying to jar loose the formula to calculate man days where 1 equals 8 hours. I have one that was given to me by a coworker:

=INT(Q3/8)+(((Q3/8)-(INT(Q3/8)))*0.8)

That calculates man days from total hours. I need a formula that will total man days and return the man day answer. Example:

weekending 12/25 = 16.2 which is 16 man days and 2 hours
weekending 1/1 = 24.7 which is 24 man days and 7 hours

Total = 41 man days and 1 hour

I have also been asked if there was a way for a number to be entered into a spreadsheet and automatically put in order without a macro or "pushing a button".

Any advice is greatly appreciated!

Happy New Year!

~ Brenda ~


I'm trying to format a worksheet to show how many days overdue certain tasks are, and running into a couple of issues. The sheet is set up with Due Dates in Column A, Days Overdue in Column B, and Date Completed in Column C. My first thought was just to use as simple a formula as possible in Column B =Today()-A2. This worked alright for tasks that already had Due Dates assigned, but if Column A was blank I'd get a high number in Column B. I also realized that tasks will continue to show as overdue even after I enter the completed-on date in Column C. Is there a relatively simple way to tackle this formula? Thanks in advance for suggestions. (I've attached an example with the column headings I want to use.)


Hello,

Please help!!!
We have a client who will pay using the 1/4, 1/2/ and 3/4 of an hour increments as follows:

From the hour mark to 6 minutes = 0 time paid
Over 7 minutes to 15 minutes = 1/4 hour 15
16 minutes to 30 minutes = 1/2 hour 30
30 minutes to 45 minutes = 3/4 hour 45
46 minutes to 60 minutes = one hour.

They work on shifts and the operation is 24 hours. Each gets 30 minutes for breaks which is not paid. Pay is biweekly and overtime is anything over 40 hours. Currently, the template we are using looks like this (sorry, I could not figure out how to paste it so you can see it in Excel layout):
WEEK 1 Sunday Monday Tuesday Wednesday Thursday Friday Saturday
5/16 5/17 5/18 5/19 5/20 5/21 5/22
TIME IN ENTER TIME, INCLUDE AM OR PM
TIME OUT
TIME IN
TIME OUT
TIME IN
TIME OUT
TIME IN Total Hours First Week
TIME OUT
HOURS WORKED-OR- choose one
*HOLIDAY WORKED
PAID HOLIDAY (not worked)
*OTHER PAID HOURS
EXPLANATION OF *HOLIDAY WORKED HRS OR *OTHER

I am very new to Excel and need help creating a formula that will allow us to calculate this timesheet? I am in desperate need for help.

Thanks..


Hi there

I am trying to calculate our On Time Delivery. I want this as a simple percentage of jobs. I have got this running in the following way:

Column M - Estimated Delivery dates
Column N - Actual Delivery dates
Column O - =IF(SUM(M2-N2)>0,1,0)

Then I have calculated On Time Delivery as: =SUM((SUM(O2:O252))/(COUNTA(N2:N252)))

This seems to work fine. My problem is, if we enter a date in Estimated without a corresponding Actual date, the formula for Column O fills out anyway and improves our On Time Delivery Percentage. How can I set this up so that the formula doesn't calculate if there is no data in Column N?

Any help much appreciated

Thanks,

James


I use Excel 2000
I have sheet muster for my clients of January, 2005 like :
( P = Present, A=Absent )
A.....B.....C.....D.....
Days Sun Mon Tue Wed
Date 1 2 3 4

1 John P A A P
2 Lucy A P P A
3
Now I want to calculate the total Sundays, Mondays, Tuesdays etc. present in
that month. How can I do this?
--
Knowldege is Power



Hi Excel experts,
I am working on a worksheet, and would like to have an entire row transferred to another worksheet based upon a certain cell's value.

Having searched through the many solved threads on this site, I attempted to customize some of the code to my worksheet. Not being proficient in Macro/VBA, I failed. I figured I would ask for help, and see if anyone can provide what I am looking for.

Basically, I am attempting to construct a "work in process" file, and would like all completed work to be deleted from the work in process sheet, and transferred to a sheet that contains a running list of all work completed.

Attached is an example of what I am working on. I would like Column Q (Status) to determine if a row can be moved to a sheet that contains the list of all work completed, and eliminated from the original sheet. Once Status is updated to "Complete", it would be helpful to be able to run a macro/click a button that would perform the transfer.

Can anyone assist?

Thanks!


I have a spreadsheet set up with an employees information, including the start date. After each year that the employee is working, he gets bumped up on the pay scale. For this reason, I only need to know how many years the employee has been working, rounded down to the nearest year.

This is what I have so far (hire date is in column B):

=((TODAY()-B4)/365)&" YEARS"

This function gives me a number with many decimal places.

I tried:

=ROUNDDOWN((TODAY()-B4)/365),0)&" YEARS"

It tells me I have too few arguments. Please help!


Hi Guys,
I need help....I am working production scheduling with Start and End time but there is a lunch time and tea time. Is there any formula to calculate Start time to End time with excluding lunch time?
Here is example :

Lunch time :12:00pm to 1:00pm.
Duration Process :6 hours.
Start Time (8:00am)
End time (5:00 pm)

I need a formula to calculate from Start Time 8:00am and what is the End Time? with 1 hour lunch time...

Thanks,
ET


Very new in this board. If I post this question in the wrong forum please bear with me.
There is about 20 staffs in our department and I have made a spreadsheet with 12 tabs for each month of the year Jan-Dec. If each staff have 15 days annual leave each year and how can I make a formular that can automatically calculate the balance of annual leave and entered in the tabs of the following months. For example if staff A used 5 days in Jan how can the balance of 10days be entered in the tabs from Feb-Dec. If he use another 5 days in July the remain balance of 5 days be automatically entered in the tab from Aug to Dec. Likewise if staff A took 2 days sick leave in Jan, and 2 days in Mar how can this sick days be automatically sum up in the months after. I am doing this manually at the moment and it is very time consuming and also very easy to make mistake.
Thanks and sorry for this long questions