Hello all,
I've tried searching the forums and some have touched on this but not quite. I am trying to show the amount of hours that will be needed over the next few weeks. As you can see in the sheet "Breakdown", I have a spreadsheet with four rows of total hours (B18:B21). Above that, going across (C11:Q11) are the amount of man hours available. These are linked to the cells above that for the number of people and hours available each week. These will be adjusted to fit the number of hours required (i.e. what if we added a sixth person).
So down below (C18:Q21), I want to see the hours divided up evenly between the four rows and when one row is completed, the rest of the hours will be divided up evenly among what's left. As the amount of work hours are adjusted, the numbers will adjust automatically. This would mean once a row's hours have been completed, the remainder cells in that row would be left blank.
Please let me know if you need more info. Thanks!